STATUS OF BHARATNET AS ON 24.06.2018

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,75,674 Kms (1,19,462 GPs)

2.

Optical Fibre laid

2,81,371 Kms (1,17,319 GPs)

3.

Tenders Finalized

3291 Blocks / 1,22,828 GPs

4.

Work Started*

3281 Blocks / 1,22,127 GPs

5.

Current Weekly performance of Optical Fibre laying

604Kms

6.

Current Weekly performance of OFC Pipe laying

307Kms

7.

Optical Fibre Cable Delivered on site 

3,40,371 Kms

8.

Service Ready GPs

1,12,033 GPs

* does not include the data of Andhra Pradesh 