STATUS OF BHARATNET AS ON 25.06.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,36,391 Kms (1,05,114 GPs)

2.

Optical Fibre laid

2,10,495 Kms (92,746 GPs)

3.

Tenders Finalized

3321 Blocks / 1,24,244 GPs

4.

Work Started*

3223 Blocks / 1,20,474 GPs

5.

Current Weekly performance of Optical Fibre laying

1665Kms

6.

Current Weekly performance of OFC Pipe laying

1440 Kms

7.

Optical Fibre Cable Delivered on site 

2,42,334 Kms

8.

GPON Integrated & Tested (Lit)

21,790 GPs

* does not include the data of Andhra Pradesh 