STATUS OF BHARATNET AS ON 21.05.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,29,799 Kms (1,02,670 GPs)

2.

Optical Fibre laid

2,05,818 Kms (91,082 GPs)

3.

Tenders Finalized

3366 Blocks / 1,25,366 GPs

4.

Work Started*

3203 Blocks / 1,19,667 GPs

5.

Current Weekly performance of Optical Fibre laying

414 Kms

6.

Current Weekly performance of OFC Pipe laying

1075 Kms

7.

Optical Fibre Cable Delivered on site 

2,33,829 Kms

8.

GPON Integrated & Tested (Lit)

19,095 GPs

* does not include the data of Andhra Pradesh 