STATUS OF BHARATNET AS ON 18.06.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,34,951 Kms (1,04,598 GPs)

2.

Optical Fibre laid

2,08,830 Kms (92,812 GPs)

3.

Tenders Finalized

3324 Blocks / 1,24,412 GPs

4.

Work Started*

3205 Blocks / 1,19,812 GPs

5.

Current Weekly performance of Optical Fibre laying

1534Kms

6.

Current Weekly performance of OFC Pipe laying

1182 Kms

7.

Optical Fibre Cable Delivered on site 

2,42,069 Kms

8.

GPON Integrated & Tested (Lit)

20,977 GPs

* does not include the data of Andhra Pradesh