STATUS OF BHARATNET AS ON 18.02.2018

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,63,702 Kms (1,16,296 GPs)

2.

Optical Fibre laid

2,64,033 Kms (1,12,360 GPs)

3.

Tenders Finalized

3327 Blocks / 1,24,154 GPs

4.

Work Started*

3279 Blocks / 1,21,921 GPs

5.

Current Weekly performance of Optical Fibre laying

1086 Kms

6.

Current Weekly performance of OFC Pipe laying

723 Kms

7.

Optical Fibre Cable Delivered on site 

3,30,223 Kms

8.

Service Ready GPs

1,02,855 GPs

* does not include the data of Andhra Pradesh