STATUS OF BHARATNET AS ON 26.03.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,22,067 Kms (99,183 GPs)

2.

Optical Fibre laid

1,80,733 Kms (79,643 GPs)

3.

Tenders Finalized

3348 Blocks / 1,24,806 GPs

4.

Work Started*

3106 Blocks / 1,18,637 GPs

5.

Current Weekly performance of Optical Fibre laying

1815Kms

6.

Current Weekly performance of OFC Pipe laying

1425 Kms

7.

Optical Fibre Cable Delivered on site 

2,12,074 Kms

8.

GPON Integrated & Tested (Lit)

17,054 GPs

* does not include the data of Andhra Pradesh