STATUS OF BHARATNET AS ON 23.04.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,26,446 Kms (101,578 GPs)

2.

Optical Fibre laid

2,04,322 Kms (90,564 GPs)

3.

Tenders Finalized

3356 Blocks / 1,24,948 GPs

4.

Work Started*

3135 Blocks / 1,18,911 GPs

5.

Current Weekly performance of Optical Fibre laying

345 Kms

6.

Current Weekly performance of OFC Pipe laying

706 Kms

7.

Optical Fibre Cable Delivered on site 

2,27,508 Kms

8.

GPON Integrated & Tested (Lit)

18,434 GPs

* does not include the data of Andhra Pradesh