STATUS OF BHARATNET AS ON 21.01.2018

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,60,695 Kms (1,15,232 GPs)

2.

Optical Fibre laid

2,58,635 Kms (1,10,848 GPs)

3.

Tenders Finalized

3334 Blocks / 1,24,757 GPs

4.

Work Started*

3276 Blocks / 1,21,918 GPs

5.

Current Weekly performance of Optical Fibre laying

941Kms

6.

Current Weekly performance of OFC Pipe laying

614Kms

7.

Optical Fibre Cable Delivered on site 

3,22,416 Kms

8.

Service Ready GPs

1,01,936 GPs

* does not include the data of Andhra Pradesh