STATUS OF BHARATNET AS ON 22.10.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,48,750 Kms (1,09,982 GPs)

2.

Optical Fibre laid

2,35,799 Kms (1,02,768 GPs)

3.

Tenders Finalized

3332 Blocks / 1,24,669 GPs

4.

Work Started*

3256 Blocks / 1,21,499 GPs

5.

Current Weekly performance of Optical Fibre laying

1472Kms

6.

Current Weekly performance of OFC Pipe laying

581Kms

7.

Optical Fibre Cable Delivered on site 

3,05,896 Kms

8.

Service Ready GPs

61,722GPs

* does not include the data of Andhra Pradesh